Schedule baselines and variance history

An authorized project Manager reviews a summary and explicitly sets a schedule baseline. Undated tasks are reported as gaps; dates are never invented. Current schedule edits do not alter saved baseline snapshots.

Open area

Steps to follow

  1. 1

    Baselines retain task identity, hierarchy, dates, duration, dependencies, milestones and the working calendar used. Grid and Timeline compare baseline and current dates using working-day variance, marking delays, earlier dates, unchanged dates and unavailable comparisons.

  2. 2

    Added tasks are marked; removed tasks retain comparison history. Rebaselining requires a reason and explicit confirmation, retains earlier versions, and identifies the current reference baseline. Select an earlier baseline for comparison.

  3. 3

    Setting a baseline approves neither execution nor resource allocations and does not change official project health. Whole-schedule deletion preserves baselines, task history and audit history.