Project Portfolio & Resource Management
Plan schedules in Grid, Timeline and Kanban
Manage task hierarchy, dependencies, progress and baseline comparisons from a project schedule.
Steps to follow
- 1
Open a project and its schedule. Use Grid for detailed editing, Timeline for dates and dependencies, and Kanban for status.
- 2
Create tasks and subtasks. Use row menus to insert, reorder and organize work. Set dates, duration and supported dependencies; review validation messages before saving.
- 3
Use the small calendar beside Start or Finish. Choose MM/DD/YYYY or DD/MM/YYYY for date display. Kanban cards start collapsed; expand a card to inspect its details.
- 4
Update progress where your role allows it. Import or export schedules and save a baseline to compare later changes.